| This chapter presents the project management approach adopted for the development of Screen2Green. Since the project combines hardware development, | This chapter presents the project management approach adopted for the development of Screen2Green. Since the project combines hardware development, | ||
| - | To address this, the team adopted a hybrid project management approach combining elements of Scrum and Waterfall. Waterfall was useful for planning around fixed academic deadlines and mandatory deliverables established by the EPS programme, while Scrum supported iterative development, | + | To address this, the team adopted a hybrid project management approach combining elements of Scrum and Waterfall. Waterfall was useful for planning around fixed academic deadlines and mandatory deliverables established by the European Project Semester (EPS) programme, while Scrum supported iterative development, |
| The chapter is organized into the main areas relevant to project management: scope, time, cost, quality, people and stakeholder management, communication, | The chapter is organized into the main areas relevant to project management: scope, time, cost, quality, people and stakeholder management, communication, | ||
| Line 141: | Line 141: | ||
| ^ Component^ Estimated cost (€) ^ | ^ Component^ Estimated cost (€) ^ | ||
| | Power supply 12VDC 2A|9.50 €| | | Power supply 12VDC 2A|9.50 €| | ||
| - | | Valve (CWX-25S CR02, 12DVC)| 33.15 €| | + | | Solenoid |
| + | | Water pump| 10.40 €| | ||
| | Buck converter | 2.50 €| | | Buck converter | 2.50 €| | ||
| | ESP32 Dev board | 9.90 € | | | ESP32 Dev board | 9.90 € | | ||
| - | | Relay module (1-ch) | 3.20 €| | + | | Relay module (1-ch) |
| | Capacitive soil moisture sensor | 4.90 €| | | Capacitive soil moisture sensor | 4.90 €| | ||
| | Temperature sensor (DS18B20)| 5.80 €| | | Temperature sensor (DS18B20)| 5.80 €| | ||
| Line 153: | Line 154: | ||
| | Red LED (5 mm)| 0.36 €| | | Red LED (5 mm)| 0.36 €| | ||
| | Resistor 470 Ω| 0.15 €| | | Resistor 470 Ω| 0.15 €| | ||
| - | |**Total estimated prototype cost**| **72.44 €**| | + | |**Total estimated prototype cost**| **62.39 €**| |
| </ | </ | ||
| </ | </ | ||
| - | The effective prototype cost was calculated to approximately | + | The effective prototype cost was calculated to approximately |
| - | During development, | + | During development, |
| - | During prototype testing, several additional components were temporarily introduced into the system to evaluate and demonstrate the watering functionality while alternative valve solutions were investigated. These components were not intended to be part of the final product but were necessary to create sufficient water pressure and validate the irrigation mechanism during testing. | + | During prototype testing, several additional components were temporarily introduced into the system to evaluate and demonstrate the watering functionality while alternative valve solutions were investigated. These components were not intended to be part of the final product but were necessary to create sufficient water pressure and validate the irrigation mechanism during testing. |
| <WRAP center round box 60%> | <WRAP center round box 60%> | ||
| Line 167: | Line 168: | ||
| < | < | ||
| ^ Component^ Quantity^ Cost (€)^Notes | ^ Component^ Quantity^ Cost (€)^Notes | ||
| - | |Water pump|1|0.00|Provided by university| | + | |Water pump|1|10.40|Provided by university| |
| - | |Water reservoir (bucket)|1|0.00|Provided by university| | + | |Water reservoir (bucket)|1|3|Provided by university| |
| - | |Tubing|2|0.00|Provided by university| | + | |Tubing|2|1.00|Provided by university| |
| - | |Nozzle|2|0.00|Provided by university| | + | |Nozzle|2|1.00|Provided by university| |
| </ | </ | ||
| </ | </ | ||
| Line 185: | Line 186: | ||
| < | < | ||
| ^ Cost category^ Description ^ Estimated cost (€) ^ | ^ Cost category^ Description ^ Estimated cost (€) ^ | ||
| - | | Prototype materials| Electronic components, sensors, irrigation system, power supply, and prototype assembly|72.44 €| | + | | Prototype materials| Electronic components, sensors, irrigation system, power supply, and prototype assembly|77.79 €| |
| |Personnel costs|Six team members, 1050 estimated working hours at 30 € per hour|31500 € | | |Personnel costs|Six team members, 1050 estimated working hours at 30 € per hour|31500 € | | ||
| |Marketing services|Estimated monthly marketing budget including social media advertising, | |Marketing services|Estimated monthly marketing budget including social media advertising, | ||
| - | |**Total estimated project value**| | **33112.44 €**| | + | |**Total estimated project value**| | **33117.79 €**| |
| </ | </ | ||
| </ | </ | ||
| Line 246: | Line 247: | ||
| For the Screen2Green project, the following stakeholders have been identified: | For the Screen2Green project, the following stakeholders have been identified: | ||
| - | * Unordered List ItemProject | + | * Project |
| * ISEP Supervisors: | * ISEP Supervisors: | ||
| - | |||
| * Young Adults: This target market group consists of the primary end users. Their needs regarding screen time reduction and user experience are the main drivers for the product' | * Young Adults: This target market group consists of the primary end users. Their needs regarding screen time reduction and user experience are the main drivers for the product' | ||
| - | |||
| * ISEP 3D Printing: As a technical stakeholder within the university, this department is essential for the fabrication of the physical pot components. Access to these resources directly impacts the prototyping schedule. | * ISEP 3D Printing: As a technical stakeholder within the university, this department is essential for the fabrication of the physical pot components. Access to these resources directly impacts the prototyping schedule. | ||
| - | |||
| * YouTube Creators: These external partners are vital for the marketing strategy. They serve as influencers who build product credibility and awareness through video content and demonstrations. | * YouTube Creators: These external partners are vital for the marketing strategy. They serve as influencers who build product credibility and awareness through video content and demonstrations. | ||
| - | |||
| * Mauser.pt: This is the primary supplier for the project' | * Mauser.pt: This is the primary supplier for the project' | ||
| - | |||
| * Online Retailers: Platforms such as Amazon and Ebay are identified as distribution stakeholders. They represent the primary channels through which the product will reach a global market. | * Online Retailers: Platforms such as Amazon and Ebay are identified as distribution stakeholders. They represent the primary channels through which the product will reach a global market. | ||
| Line 293: | Line 288: | ||
| Manage Closely (High Power, High Interest): This category includes Team 1 and ISEP Supervisors. Communication here must be frequent and highly detailed. The team will use regular face-to-face meetings, constant messaging, and technical reports to ensure everyone is aligned. | Manage Closely (High Power, High Interest): This category includes Team 1 and ISEP Supervisors. Communication here must be frequent and highly detailed. The team will use regular face-to-face meetings, constant messaging, and technical reports to ensure everyone is aligned. | ||
| - | Keep Satisfied (High Power, Low Interest): This category includes the ISEP 3D Printing lab and the supplier Mauser.pt. Communication should be strictly professional, | + | * Keep Satisfied (High Power, Low Interest): This category includes the ISEP 3D Printing lab and the supplier Mauser.pt. Communication should be strictly professional, |
| - | + | | |
| - | Keep Informed (Low Power, High Interest): This category includes the target market of Young Adults and YouTube Creators. Communication needs to be engaging and visual. The team will share project updates, app teasers, and promotional videos on social media to build excitement without requiring technical involvement. | + | |
| - | + | ||
| - | Monitor (Low Power, Low Interest): This category covers Online Retailers. No direct communication is required during the prototype phase. The team will simply observe these platforms for competitor trends and pricing until the product is ready for mass distribution. | + | |
| Line 445: | Line 438: | ||
| === 3.8.1 Definition === | === 3.8.1 Definition === | ||
| - | Procurement Definition | ||
| - | The project requires specific hardware and materials to build a functional prototype. The following items must be purchased: | ||
| - | Electronic components: ESP32 board, 12 VDC pilot-operated solenoid | + | The project requires specific hardware and materials to build a functional prototype. |
| + | |||
| + | The following items must be purchased: | ||
| + | |||
| + | * Electronic components: ESP32 board, 12 VDC valve, capacitive soil moisture sensor, DS18B20 temperature sensor, relay module, buck converter, 8W submersible pump, and power supply. These are required for the automated irrigation system prototype. | ||
| + | * Hardware fittings: A brass 1/2 inch female hose adapter to connect the pump and valve. | ||
| + | * Structural materials: Biodegradable PLA filament and natural cork to construct the pot and water tank. | ||
| - | Hardware fittings: A brass 1/2 inch female hose adapter to connect the pump and valve. | ||
| - | Structural materials: Biodegradable PLA filament and natural cork to construct the pot and water tank. | ||
| === 3.8.2 Suppliers === | === 3.8.2 Suppliers === | ||