 <table project_milestones> <table project_milestones>
 <caption>The main milestones of the project</caption> <caption>The main milestones of the project</caption>
-^ Date ^ Milestone^ +^ Date ^ Milestone ^ Project day 
-| 2026-02-23    | Project start | +| 2026-02-23    | Project start | 0 
-| 2026-02-28    | Selection of preferred project proposals    | +| 2026-02-28    | Selection of preferred project proposals    | 5 
-| 2026-03-11    | Upload black box diagram and structural drafts    | +| 2026-03-11    | Upload black box diagram and structural drafts    |16
-| 2026-03-18    | Upload initial list of components and materials   | +| 2026-03-18    | Upload initial list of components and materials   |23
-| 2026-03-21    | Define project backlog, global sprint plan, initial sprint plan, and Gantt chart (Jira)   | +| 2026-03-21    | Define project backlog, global sprint plan, initial sprint plan, and Gantt chart (Jira)   |26
-| 2026-03-25    | Upload detailed system schematics and structural drawings   | +| 2026-03-25    | Upload detailed system schematics and structural drawings   |30
-| 2026-04-12    | Upload interim report and presentation   | +| 2026-04-12    | Upload interim report and presentation   |48
-| 2026-04-16    | Interim presentation and feedback   | +| 2026-04-16    | Interim presentation and feedback   |52
-| 2026-04-22    | Upload 3D model video   | +| 2026-04-22    | Upload 3D model video   |58
-| 2026-04-29    | Upload final list of materials   | +| 2026-04-29    | Upload final list of materials   |65
-| 2026-05-02    | Upload refined interim report   | +| 2026-05-02    | Upload refined interim report   |68
-| 2026-05-13    | Upload packaging solution +| 2026-05-13    | Upload packaging solution  |79
-| 2026-05-27    | Upload functional test results   | +| 2026-05-27    | Upload functional test results   |93
-| 2026-06-13    | Upload final report, presentation, video, paper, poster, and manual   | +| 2026-06-13    | Upload final report, presentation, video, paper, poster, and manual   |110
-| 2026-06-18    | Final presentation, discussion, and assessment   | +| 2026-06-18    | Final presentation, discussion, and assessment   |115
-| 2026-06-23    | Final corrections and upload of refined deliverables   | +| 2026-06-23    | Final corrections and upload of refined deliverables   |120
-| 2026-06-25    | Prototype demonstration and final submission   |+| 2026-06-25    | Prototype demonstration and final submission   |123|