| log [2026/05/20 23:19] – [[Retrospect] 10th Presentation Meeting (2026-05-21)] team1 | log [2026/06/03 14:12] (current) – [[Retrospect] 12th Presentation Meeting (2026-06-03)] team1 | ||
|---|---|---|---|
| Line 372: | Line 372: | ||
| ==== [Retrospect] 10th Presentation Meeting (2026-05-21) ==== | ==== [Retrospect] 10th Presentation Meeting (2026-05-21) ==== | ||
| - | 1. Writing related work | + | 1. Revised poster |
| - | 2. Revised leaflet + flyer | + | 2. Packaging solution |
| 3. Solid works model for testing | 3. Solid works model for testing | ||
| Line 380: | Line 380: | ||
| 4. Future focuses | 4. Future focuses | ||
| + | === Minutes === | ||
| + | |||
| + | The teacher liked both of the poster designs, so we have to talk to Anna (communication) to get a final feedback on which to choose based on what is most important. The packaging solution is better, but we can move some words to more visible places so it doesn' | ||
| + | |||
| + | ==== [Retrospect] 11th Presentation Meeting (2026-05-28) ==== | ||
| + | |||
| + | 1. Posters | ||
| + | |||
| + | 2. App update + test results | ||
| + | |||
| + | 3. Assembled circuit + test results | ||
| + | |||
| + | 4. Scientific paper | ||
| + | |||
| + | ==== [Retrospect] 12th Presentation Meeting (2026-06-03) ==== | ||
| + | |||
| + | ==Agenda;== | ||
| + | * 3d print | ||
| + | * strenght testing | ||
| + | * app updates | ||
| + | * user manual | ||
| + | * scientific paper | ||
| + | |||
| + | |||
| + | === Minutes === | ||
| + | |||
| + | Scientific paper: | ||
| + | |||
| + | - Testing of the prototype: Tests we did, conditions we used, the results leading to, factors of safety, impact of that | ||
| + | |||
| + | - Impact on latency for the app, loading | ||
| + | |||
| + | - k6: remove this | ||
| + | |||
| + | Video, up to 3 minutes: | ||
| + | |||
| + | - Use our colors | ||
| + | |||
| + | - What it is | ||
| + | |||
| + | - How to use | ||
| + | |||
| + | - Why | ||
| + | |||
| + | - The outcomes | ||
| + | |||
| + | - The team | ||
| + | |||
| + | Can look at the previous years and their videos. | ||
| + | |||
| + | Testing: | ||
| + | |||
| + | - Identify the load cases, impact, etc - lateral, vertical, worst scenario | ||
| + | |||
| + | - Falls on the floor: 1m f.eg, a child kicking it f.eg. | ||
| + | |||
| + | - Send the results to JFJ | ||
| + | |||
| + | - Conclude with factors | ||
| + | |||
| + | User manual: | ||
| + | |||
| + | - Don’t include the team members | ||
| + | |||
| + | - The product, qr code for the wiki | ||
| + | |||
| + | - Date is fine, commercial user manual | ||
| + | |||
| + | - Product image: with a siluette of a human, interacting a bit or something, a human element | ||
| + | |||
| + | - An image of the electrical has their own space | ||
| + | |||
| + | - Watering: can do it on their own also. | ||
| + | |||
| + | - Natural plant cycle —> estimated time limit. 3-6 months. Mention in the Wiki. Seringador —> a cultivation guide | ||
| ===== Activities ===== | ===== Activities ===== | ||
| //Please register here all accomplished project activities// | //Please register here all accomplished project activities// | ||
| Line 398: | Line 473: | ||
| |15.04.26|16.04.26|Interim rehearsal|The team physically came together to rehearse the interim presentation and timing it|Entire team| | |15.04.26|16.04.26|Interim rehearsal|The team physically came together to rehearse the interim presentation and timing it|Entire team| | ||
| |16.04.26|16.04.26|Interim presentation|Present our product idea at the interim presentations|Entire team| | |16.04.26|16.04.26|Interim presentation|Present our product idea at the interim presentations|Entire team| | ||
| - | |19.04.26|19.04.26|Start coding project|Started the front end project and initialize | + | |19.04.26|19.04.26|Start coding project|Started the front end project and initialized |
| + | |20.04.26|20.04.26|Add authentication|Added authentication in the application, | ||
| |24.04.26|24.04.26|Mail about water beads|Requested to hold a meeting with Cristina Ribeiro to discuss soil-replacing water beads|Hanna| | |24.04.26|24.04.26|Mail about water beads|Requested to hold a meeting with Cristina Ribeiro to discuss soil-replacing water beads|Hanna| | ||
| |26.04.26|26.04.26|Initialize back end|Initialized the Supabase back-end and activated auth functionality|Avkaran| | |26.04.26|26.04.26|Initialize back end|Initialized the Supabase back-end and activated auth functionality|Avkaran| | ||
| |30.04.26|30.04.26|Personal meeting about water beads|Hold a meeting with Cristina Ribeiro to discuss soil-replacing water beads|Entire team| | |30.04.26|30.04.26|Personal meeting about water beads|Hold a meeting with Cristina Ribeiro to discuss soil-replacing water beads|Entire team| | ||
| |07.05.26|07.05.26|Initial leaflet design|Make the first design for the leaflet|Sophie| | |07.05.26|07.05.26|Initial leaflet design|Make the first design for the leaflet|Sophie| | ||
| + | |13.05.26|13.05.26|Poster & Leaflet design|Finished the design and reviewed it in class|Sophie| | ||
| + | |20.04.26|26.05.26|Complete routing in app|Added all the pages in the application (landing, social zone, profile, plant stats and focus timer)|Avkaran| | ||
| + | |22.05.26|28.05.26|App testing|Finished the required tests for the deliverable|Avkaran| | ||